Next steps
Work on the next phase, the construction of the foundations of two new road bridges, started in September 2009.The construction and assembly of the bridges, along with the demolition of the old bridges, is expected to take until early 2011.
More cycle lanes and footways are still to be completed, in addition to two new signalised pedestrian crossings and landscaping to make the area more attractive and safer for pedestrians and cyclists to use.
The full scheme is currently scheduled to be complete by summer 2011.
Download a map of the proposed changes (PDF 144KB)
Schedule of Work
The schedule of works below outlines when key construction activities will take place until completion in 2011.
Late 2009
- Excavations and construction of the foundation for both bridges
Early 2010
- Both Waldgrave Bridge and the new South Bridge supports will be built ready for the construction of the bridges in mid 2010
Mid 2010
- The new South Bridge is being built on a plot of land to the west of Hanger Lane and will be driven into location over three weekends
Late 2010
- The Waldegrave Bridge will be constructed before the old bridge is demolished, safety barriers and surfacing will be completed before 2011
-
The new South Bridge will be finished at the end of 2010 with safety barriers installed and surfacing works taking place in late 2010
-
The remaining cycle lanes and footpath will be constructed at the end of 2010 and will be completed in early 2011
-
The majority of the utility works will be completed in 2010
2011
-
The new pedestrian and bicycle signalised crossing, and pedestrian crossing will be installed before resurfacing takes place
-
The final landscaping will be completed in late 2011
Transport for London


